﻿WEBVTT

1
00:00:00.000 --> 00:00:09.840
CEI - NASA Santa Susana Coca Hydrogen Ball Demolition, May 29 - August 16, 2018

2
00:00:09.840 --> 00:00:12.200
Day 1 – May 29, 2018 - staging of the area with equipment

3
00:00:12.200 --> 00:00:14.880
Day 2 – May 30, 2018 - staging of the area with equipment

4
00:00:14.880 --> 00:00:17.560
Day 3 – May 31, 2018 - staging of the area with equipment

5
00:00:17.560 --> 00:00:20.240
Day 4 – June 1, 2018 - the bottom fifth of the sphere starts to be removed

6
00:00:20.240 --> 00:00:22.440
Day 5 – June 11, 2018 - a crane is staged at the work site

7
00:00:22.440 --> 00:00:26.240
Day 6 – June 12, 2018 - work site preparations

8
00:00:26.240 --> 00:00:30.040
Day 7 – June 13, 2018 - work site preparations

9
00:00:30.040 --> 00:00:33.840
Day 8 - June 14, 2018 - the crane is poised at the top of the sphere where a worker begins to make cuts into the top portion

10
00:00:33.840 --> 00:00:37.280
Day 9 - June 15, 2018 - the crane is poised at the top of the sphere where a worker begins to make cuts into the top portion

11
00:00:37.280 --> 00:00:41.040
Day 10 - June 18, 2018 - the crane is poised at the top of the sphere where a worker begins to make cuts into the top portion

12
00:00:41.040 --> 00:00:44.840
Day 11 - June 19, 2018 - remaining portion of top of spehere is removed

13
00:00:44.840 --> 00:00:48.640
Day 12 - June 21, 2018 - preparations for removal of top fifth of sphere

14
00:00:48.640 --> 00:00:51.440
Day 13 - June 22, 2018 - the top fifth of the sphere starts to be removed

15
00:00:51.440 --> 00:00:55.120
Day 14 - June 25, 2018 - cuts are made downward into the next portion of the sphere

16
00:00:55.120 --> 00:00:58.920
Day 15 - June 26, 2018 - cuts continue to be made on the top portion of the sphere

17
00:00:58.920 --> 00:01:02.720
Day 16 - June 27, 2018 - sections along the top portion of the sphere are removed

18
00:01:02.720 --> 00:01:06.520
Day 17 - June 28, 2018 - continued removal of sections along the top portion of the sphere

19
00:01:06.520 --> 00:01:10.320
Day 18 - June 29, 2018 - continued removal of sections along the top portion of the sphere

20
00:01:10.320 --> 00:01:14.120
Day 19 - June 30, 2018 - continued removal of sections along the top portion of the sphere

21
00:01:14.120 --> 00:01:16.280
Day 20 - July 2, 2018 - continued removal of sections along the top portion of the sphere

22
00:01:16.280 --> 00:01:18.600
Day 21 - July 3, 2018 - continued removal of sections along the top portion of the sphere

23
00:01:18.600 --> 00:01:23.360
Day 22 - July 5, 2018 - continued removal of sections along the top portion of the sphere


24
00:01:23.360 --> 00:01:27.040
Day 23 - July 6, 2018 - continued removal of sections along the top portion of the sphere

25
00:01:27.040 --> 00:01:32.120
Day 24 - July 10, 2018 - continued removal of sections along the top portion of the sphere

26
00:01:32.120 --> 00:01:37.240
Day 23 - July 11, 2018 - continued removal of sections along the top portion of the sphere

27
00:01:37.240 --> 00:01:42.280
Day 26 - July 12, 2018 - sections along the back top portion of the sphere are  cut and removed


28
00:01:42.280 --> 00:01:45.880
Day 27 - July 13, 2018 - continued removal of sections along the back top portion of the sphere

29
00:01:45.880 --> 00:01:50.960
Day 28 - July 16, 2018 - continued removal of sections along the back bottom portion of the sphere

30
00:01:50.960 --> 00:01:56.040
Day 29 - July 17, 2018 - continued removal of sections along the back bottom portion of the sphere

31
00:01:56.040 --> 00:01:59.840
Day 30 - July 18, 2018 - continued removal of sections along the back and front bottom portions of the sphere

32
00:01:59.840 --> 00:02:04.920
Day 31 - July 23, 2018 - sections of the bottom front portion of the sphere are removed


33
00:02:04.920 --> 00:02:10.000
Day 32 - July 24, 2018 - the removal of the bottom portion of the sphere is completed; only the middle section remains

34
00:02:10.000 --> 00:02:15.080
Day 33 - July 25, 2018 - cutting and removing sections of the middle portion of the sphere

35
00:02:15.080 --> 00:02:20.160
Day 34 - July 26, 2018 - continued cutting and removing sections of the middle portion of the sphere

36
00:02:20.160 --> 00:02:25.240
Day 35 - July 30, 2018 - continued cutting and removing sections of the middle portion of the sphere

37
00:02:25.240 --> 00:02:30.200
Day 36 - July 31, 2018 - continued cutting and removing sections of the middle portion of the sphere

38
00:02:30.200 --> 00:02:35.320
Day 37 - August 1, 2018 - continued cutting and removing sections of the middle portion of the sphere

39
00:02:35.320 --> 00:02:40.400
Day 38 - August 2, 2018 - continued cutting and removing sections of the middle portion of the sphere

40
00:02:40.480 --> 00:02:45.440
Day 39 - August 14, 2018 - continued cutting and removing the remaining sections of the middle portion of the sphere

41
00:02:45.440 --> 00:02:50.600
Day 40 - August 15, 2018 - continued cutting and removing sections of the middle portion of the sphere

42
00:02:50.600 --> 00:02:55.560
Day 41 - August 16, 2018 -  the removal of the middle portion of the sphere is completed, and then an excavator removes nine supporting beams remain